AI Data Centers Are Buying Used Jet Engines as New Power Turbines Take Six Years
AI data-center developers are hunting for used gas turbines and retired jet engines because ordering brand-new power equipment could leave their servers waiting for electricity until the next decade.
Some companies are buying refurbished machines, while others are converting aircraft-engine technology into generators that can run alongside their computing facilities.
New gas turbines now take an average of six years to deliver in the United States, according to energy consultancy Wood Mackenzie. Delivery discussions are already focused on 2030 and 2031, a timeline that clashes with an AI industry trying to bring enormous computing campuses online much sooner.
Global turbine orders have topped 100 gigawatts, compared with manufacturers' estimated annual capacity of just 60 to 70 gigawatts, Reuters reported. Siemens Energy, GE Vernova, and Mitsubishi Heavy Industries have all said orders are outpacing what they can produce.
Gas turbines can generate large amounts of electricity by burning natural gas to spin equipment connected to a generator. AI data centers need that power around the clock to run densely packed chips and cooling systems, and connecting new facilities to public electricity grids can itself take years.
The International Energy Agency expects global data-center electricity consumption to nearly double from 485 terawatt-hours in 2025 to 950 in 2030. Consumption at AI-focused facilities is projected to triple over the same period.
From airplane engines to AI power plants
One way around the backlog is an aeroderivative turbine, a power generator built using technology adapted from aircraft jet engines.
Other companies are going further by seeking older machines and retired aircraft engines that can be rebuilt for stationary power production. For example, AI infrastructure firm Crusoe ordered 13 units from Missouri-based ProEnergy in April, each rated at 50 megawatts, for a combined 650 megawatts. The jet-engine-derived equipment is intended for future U.S. data centers, but the contract doesn't mean that Crusoe bought engines removed from retired aircraft.
Second-hand machines can also carry a substantial discount. Used turbines in good condition sell for about $1.5 million to $1.7 million per megawatt, compared with roughly $2 million to $2.5 million for new units, according to equipment brokers and energy analysts interviewed by Reuters.
One broker described a sale of two smaller turbines totaling 29 megawatts for $12.5 million. Equivalent new equipment would have cost about $35 million and taken five years to arrive, he said.
"That secondary market is very, very hot right now," EthosEnergy CEO Ana Amicarella told Reuters, adding that asking prices are climbing as more buyers compete for the same machinery.
The problem with second-hand power
Building a power plant beside a data center also brings fuel needs, air emissions, and permits into the equation. The Environmental Protection Agency says stationary turbines and engines used by data centers are subject to federal air-pollution standards.
Last week, OpenAI promised to cover electricity and grid costs at future campuses it owns and operates after voters backed tighter restrictions on data-center construction.
Power-market research firm Cleanview identified about 90 gigawatts of proposed on-site generation at U.S. data centers in its mid-2026 analysis. Only about 2 gigawatts was operating at the time.
Developers are looking beyond turbines, too. Finnish manufacturer Wärtsilä told Reuters it had booked around 3 gigawatts of orders from U.S. data centers since spring 2025 for generators powered by gas engines rather than turbines.
-- Price
This content is provided for general informational purposes only and doesn't constitute financial, investment, legal, or tax advice. Any events, rewards, online promotions, or related information mentioned herein should not be considered a recommendation, solicitation, or invitation to purchase, sell, trade, or otherwise deal in any crypto assets. Crypto assets are highly volatile and may result in loss. The availability of WEEX services, products, and related events may vary by region. You are responsible for ensuring that your participation is in accordance with applicable local laws and regulations.
You may also like

Crypto: Ethereum Prepares Two Solutions to Protect Its Smart Contracts

Heating by Mining Bitcoin? Finnish Families Are Trying This 'Free' Heating

Elysium Mainnet Launches with Block Time of 100 Milliseconds and Arrival Time of Approximately 300 Milliseconds

Samsung Etching Process Formulas Flow to Lam Research Korea

Raycash Launches on Ethereum Mainnet, Offering Privacy Stablecoin Payments and Yield Features

South Korean Deputy Prime Minister Says AI Data Center Regulation Needs Observation After U.S. Midterm Elections

Ave.ai Supports Elysium Ecosystem, Opens Cross-Chain and On-Chain Trading Capabilities

Who Will Bear the Cost of Delays in AI Data Centers?

Ethereum Releases Gas Repricing EIP Draft

Ethereum Developers Call for Halt to Gelmsterdam Upgrade

Vitalik: High Intervention Governance Needed for Fee Burn, May Drive Up Gas Prices

Anthropic Acquires $3.4 Billion Gas Power Equipment

Google buys Crusoe's data center in Wyoming for $17 billion

EIP-8037 state-gas rules force Ethereum dApps to rewrite billing

Stablecoins offer sub-cent payments, Armstrong says, as critics flag risks

Democratic Party's AI Regulation Push Revealed: Plans for Intensive Legislation and Strict Scrutiny of Tech Giants

Ethereum Foundation Reminds Contract Developers to Self-Check Impact of Glamsterdam Gas Adjustments

Breaking Down Bitcoin Trends: What Determines the True Value of L1?

Yushu and PetroChina Jointly Establish Industrial Embodied Intelligence Company with Kunlun Manufacturing Holding 60%

ZetaChain Proposes L1 Shutdown Amid Solana Migration, Plans to Burn 55 Million ZETA

SemiAnalysis: Musk Breaks Through Again, How SpaceX Competes for the World's Largest AI Cloud?

What is Qtum (QTUM)? A Proof-of-Stake Smart Contract Chain

Important News from Last Night and This Morning (November 4 - November 5)

FERC Approves MARA's Acquisition of Long Ridge Natural Gas Power Plant

Ethereum Economic Zone enters code implementation stage for liquidity bridging

Gnosis Chain Ends Independent L1 Operations in Spring 2027, Joins EEZ as First General-purpose Zone

Bloomberg analyst identifies boom-bust pattern in BTC and commodities

Ethereum Economic Zone unveils three cross-chain breakthroughs at Devcon

BNB Chain InsurancePool Suffers Flash Loan Attack with Losses of Approximately $111,000